Construction Update: from the Board of Education meeting of March 26, 2009
Update report from Jim Ronning, representing Henry Bros. Construction.
Lincoln-Way West project continues in a safe quality manner, on schedule and under budget. Locker installations are now complete in the Academic wing, Fine Arts and Physical Education buildings.Installationof the Auditorium acoustic wall panels has been completed. Application of the final coat of painting continues throughout the Fine Arts building. Installation of the Academic building acoustical ceilings is near completion. Carpet installation continues on throughout the Academic building. Installation of the public corridor floor tiles continues, and application of the final coat of painting continues throughout the Academic building. Installation of the field house Mondo rubber flooring continues, as well as the installation of the gym overhead lighting. Installation ofthe gym sound system and gym athletic equipment is completed,